Nuclear power plant's construction project can be roughly devided into two: constructing the nuclear power plant itself as well as preparing the site and building other necessary buildings in the area.

Hanhikivi 1 timeline
2015
  • Registration of subcontractors started.
  • Fennovoima continued to grow rapidly, doubling its personnel. Recruitment brought in project and nuclear safety knowhow, in particular.
  • Trees were felled in the spring and summer.
  • The first electric stations were finished at the site.
  • Fencing of the power plant area started.