Fennovoima and Rusatom Overseas signed in December 2013 a plant supply contract for the Hanhikivi 1 nuclear power plant to be built in Pyhäjoki. The contract is managed by Rosatom Energy International’s Finnish subsidiary RAOS Project Oy.
- Customer: Fennovoima Oy
- General contractor: RAOS Project Oy
- Number of units: 1
- Capacity: 1200 MW (Reactor of WWER-type)
- Referential NPP: Leningradskaya NPP-2 (LAES-2), Sosnovyj Bor
- Location: the cape Hanhikivi, Pyhäjoki peninsula, North Ostrobothnia region, Baltic sea shore